Although we quit an hour early today, we felt that we have given a great deal, even more finished than was expected. Accomplishments:
Trim installed through both units, caulked, sanded, and painted two coats.
Interior doors painted two coats.
Door frames on 4 exterior doors, caulked, sanded, and painted.
Exterior doors painted.
Holes dug, posts set up and 2 pads built for air conditioning units.
Both pairs of front steps sanded clean and ready for staining.
Trough dug (tough work) for sidewalk's concrete ... Due for pouring next week.
Clean up of front yard of neighboring abandoned house.
And major project: insulation blown from attic crawl space into wall spaces. ( see below )
SUITED UP AND BLOWING INSULATION ...
MORE ON THE SITE TODAY:
TAKING A BREAK...
FINAL GROUP SHOT...